Solution · utility
Utility-Scale Solar Plant
>5 MWp utility-scale block built around the SG6250HV-MV central inverter and medium-voltage integration.
Request quote for this stackBill of materials
| Role | Product | Qty |
|---|---|---|
| Central inverter (6.25 MW block) | Sungrow Sungrow SG6250HV-MV | 1 |
| PV modules (6.15 MWp) | Jinko Jinko Tiger Neo 615W Solar Panel | 10000 |
For utility-scale projects above 5 MWp, trientec supplies complete block configurations around the Sungrow SG6250HV-MV central inverter. Each 6.25 MW block pairs with approximately 10,000 Jinko Tiger Neo modules and connects directly to medium voltage via the inverter’s integrated MV transformer.
Project delivery
Trientec provides logistics coordination for container-scale deliveries, direct factory shipment to site, and equipment commissioning liaison with the EPC contractor. Lead times for SG6250HV-MV are 8–14 weeks depending on configuration; we advise early order placement for projects with fixed grid connection deadlines.